The gallery at Black Robin Farm is now due in 2028 and the café, shop and heritage gallery by 2030. In 2024 the council expected building to start that year.

The new gallery at Black Robin Farm, on the Downs above Eastbourne, is now due to be finished in 2028. The rest of the arts centre, including the heritage gallery, the shop and the café or restaurant, is aiming for 2030.

Eastbourne Borough Council set out the timetable in a statement published on 10 November, “in response to recent questions about the plans”. It said the vision “remains unchanged” but that “the timetable has evolved”.

When the scheme was first approved in February 2024, the council’s own announcement said: “It is expected work will begin on the centre at Black Robin Farm in 2024.” Building has not yet started at the farm itself.

What has changed

The project is now being built in two phases. The council’s statement gives the reasons as the work needed to satisfy planning and ecological conditions, and “changing economic conditions”.

Phase 1, due to finish in 2028, includes:

  • moving the existing farm business permanently to Ringwood Farm, with a new barn, farmyard and drainage
  • the new gallery building
  • “elements of” the events and education barn
  • power, water and other services, landscaping and habitat work
  • parking, a bus turning circle and a dedicated bus stop

Phase 2, aiming to finish by 2030, covers the heritage gallery and engagement spaces, and a permanent shop and café or restaurant.

Phase 2 depends on money that has not yet been secured. The council says Towner won a development grant from the National Lottery Heritage Fund in 2025. Towner will use it to design the oldest parts of the site before it applies for a full delivery grant for the Phase 2 work.

Timeline of the Black Robin Farm project: Levelling Up Fund award of 19.8 million pounds in October 2021; national park committee approval in February 2024, when the council expected work to start that year; planning permission secured in February 2026; enabling works at Ringwood Farm under way in November 2026; grant deadline in March 2028, with the gallery and Phase 1 due in 2028; Phase 2 by 2030 if further funding is won.
How the dates have moved. Graphic by Eastbourne Live, from the council's statement, the Scrutiny Committee minutes and the council's February 2024 announcement.
Share this chartFacebookWhatsAppX

What councillors were told

Councillors questioned officers about the delays at the council’s Scrutiny Committee on 2 November. The minutes record that:

  • planning permission was secured in February 2026, after “a complex and lengthy planning process”
  • enabling works at Ringwood Farm have started
  • work at Black Robin Farm “remained on track” for the grant deadline of March 2028
  • officers are still discharging planning conditions and securing ecological licences, because protected species live on the site

Asked whether parts of the scheme had been cut because of rising building costs, officers said the project had been re-phased. The key infrastructure and the gallery come first. Education spaces and other visitor facilities would come forward “through subsequent funding opportunities”.

The minutes also record that the council is responsible for delivering the current phase and for managing the grant money. It works with Towner on the later phases.

The South Downs National Park Authority’s planning committee approved the plans on 15 February 2024, subject to conditions. These included a legal agreement to secure an expanded bus service and a new public footpath. The authority said the centre was estimated to attract up to 100,000 visitors a year.

Where the money comes from

The scheme is funded mainly by the government’s Levelling Up Fund. The council won £19.8 million for it, a figure given on Towner’s project page, and its statement says the award was made in October 2021. The council says the project is now being delivered “against a very different economic backdrop” from that time.

What it means for you

Nothing opens at Black Robin Farm, off Beachy Head Road, before 2028.

Over the next year, expect work traffic at Ringwood Farm and then at Black Robin Farm. The council has not published dates for construction at the main site. Towner said in August that development there begins in early 2027.

The café, shop and heritage gallery are the parts most visitors would use, and they are the parts that still need funding. If the lottery application fails, the 2030 date is at risk. The council has not said what happens in that case.